May 2007 -- new bedroom
for the kids done. By done, as always, we mean trim work still to
happen later. New guest room done (thanks to Cindy).
-
April 2007 -- attic mostly done. Trim work remaining, moving stuff (always) in progress.
-
November 2006 -- insulated remainder of
attic.
-
October 2006 -- started finishing remainder
of attic. Frame, HVAC, and electrical done.
-
April 15, 2004 -- patio & back stairs poured.
-
January 15, 2004 -- A little over 1 year from
when we first got financing on the house for a March 2003 start date, our
house is finally (basically) done. Sarah & I did a walk through
today and came up with a small punch list of items to be fixed, but all is
relatively well. We'll still need to tile the upstairs shower and
paint the mudroom before moving on to turning the old kitchen into a
dining room. The next challenge will be figuring out how to get a
mattress to the new bedroom. A new concrete patio, stairs, and some
sidewalk will go down in the spring.
-
January 13 -- the kitchen and downstairs
bathroom are complete. Carpet will be installed upstairs today.
Need to install flooring in the upstairs bathroom and then minor details
from there. Will be done by the end of next week.
-
January 3, 2004 -- Amy McGill gets married.
-
December 31 -- Jungle gets married.
-
December 22 -- It has been going better
than these updates would appear. The downstairs bathroom & kitchen
have flooring & have been painted. Fixtures and appliances are to be
installed today. The upstairs is all painted and has lighting, just
needs flooring. The upstairs bathroom is going to wait awhile to be
finished ($$).
-
December 3 -- Ellen Jane Maupin born.
-
December 1 -- Painting has been slow.
Kitchen is painted, siding is on, cabinets are (mostly) installed.
Need to paint upstairs, install flooring & trim.
-
December 1 -- Payton Charles Messer born.
-
November 13 -- Siding is about half way on.
Progress is s - l - o - w.
-
November 6 -- Sheet rock is mostly
finished. We've started painting the kitchen. Upstairs will be
tan, black, and red. Downstairs bathroom & entry will be grey &
white. Kitchen will be considerably brighter.
-
October 30 -- Finishing up the sheet rock
mud & such, it's really starting to look like the finished product now.
-
October 25 -- Mizzou beats Texas Tech
62-31.
-
October 17 -- Insulation has started with
sheet rock and siding to follow this week.
-
October 16 -- We're all framed up, electricited up, plumbed up, and (mostly) HVACed
up, the shingles are on, waiting on city inspector.
-
October 11 -- Mizzou beats Nebraska for
first time since 1978
-
October 10 -- railing for upstairs balcony
arrived.
-
October 8 -- Cabinets and Refrigerator
arrived, no place to put them yet.
-
October 2 -- Electrical and HVAC work have
begun
-
September 30 -- Downstairs existing wall
removed (partially).
-
September 25 -- Windows & Doors in
-
September 24 -- Windows & Doors delivered,
remaining framing done.
-
September 18 -- Roof is done. Windows
& Doors next week.
-
September 16 -- Existing roof and ceiling
gone, can see the stars from the bedroom.
-
September 12 -- New part of roof framed up.
Tie into house next week.
-
September 4 -- Framing completed, roof is
next. The place looks pretty Wow big.
-
September 4 -- Adelaide takes her first
real steps
-
September 2 -- Second floor framing begins
-
August 30 -- Football season begins!
-
August 27 -- First floor framed in, floor
joists for second floor laid.
-
August 26 -- First wall up. It's not
much, but it's a wall.
-
August 19 -- Foundation done.
-
August 15 -- Jungle gets engaged.
-
August 13 -- Footings poured.
-
August 11 -- Moving dirt; preparing for
foundation work.
-
August 1 -- Reach agreement with new
contractor.
-
July 10 -- Asa Henry Smith born.
-
July 7 -- Sewer line project completed
-
July 3 -- contractor quits.
-
June 30 -- Sewer line project started
(moving sewer line)
-
June 23 -- Concrete slab removed
-
April 4, 2003 -- Tree removed (started at least)